Post contrainte

Post-stressed slab at Twenty 8 - Belval

The work included the following stages:

  • Formwork
  • Positioning of active and passive stressing heads
  • Installation of cable ducts
  • Reinforcement
  • Concreting
  • Cable tension at 100% after 12 days
  • Injection to prevent corrosion